“Our supplier said that it would take us 2 weeks to build and ship out 50 parts – we needed them by Friday. Help ” e-mail we got on Saturday evening:))))
Our clients’ assembly line requires structural housings as the product was used to get parts 3D printed at the same time, with no tooling, no molds, just a STEP file and had no time to waste.
- Sunday – File review, internal workflow check
- Monday – Order confirmed, adjusting printing builds
- Tuesday – 3D printed with MJF in PA12GB
- Wednesday – Post-processing of parts / perform QA inspections on parts
- Thursday – 50 parts delivered to the customer (local delivery)
This is how we operate every single week with our customers needing on-demand manufacturing, and in some cases, we need to push it a bit farther.
If you’re facing short timelines / low-volume or can’t get production quantities because of traditional manufacturing restrictions, contact us.