Case Study: 50 Parts Delivered in 4 Days

“Our supplier said that it would take us 2 weeks to build and ship out 50 parts – we needed them by Friday. Help ” e-mail we got on Saturday evening:))))

Our clients’ assembly line requires structural housings as the product was used to get parts 3D printed at the same time, with no tooling, no molds, just a STEP file and had no time to waste.

  • Sunday – File review, internal workflow check
  • Monday – Order confirmed, adjusting printing builds
  • Tuesday – 3D printed with MJF in PA12GB
  • Wednesday – Post-processing of parts / perform QA inspections on parts
  • Thursday – 50 parts delivered to the customer (local delivery)

This is how we operate every single week with our customers needing on-demand manufacturing, and in some cases, we need to push it a bit farther.

If you’re facing short timelines / low-volume or can’t get production quantities because of traditional manufacturing restrictions, contact us.